TRADERS UPDATED ABOUT KINGS SQUARE PROCESS

 

Kings Square

 

Only a handful of local traders turned up yesterday for an update about the building progress of the Kings Square Redevelopment Project.

These updates at the Federal Hotel have been regular events to keep affected traders in the loop.

Those who came heard form builders Pindan and Probuild, Sirona Capital and City of Fremantle Director Infrastructure and Project Delivery Graham Tattersall that things are going very well and to schedule.

Completion of our Civic Centre community facility will be in July 2020, so a construction period of 18 months. Excavation will start in two weeks for the lower level and the main structure will be up before Christmas this year, so that will give us all a much better idea of what we can expect and how it works in the space.

Sirona is on the home straight with their two buildings and they are estimated to be completed by August/September this year. The paving of Newman Court on the Sirona side will be done in September and the Civic Centre half toward completion of that building.

Queen Street should be back to normal in July when the hoarding there comes down, so that will make traffic flow a bit easier.

The Newman Court thoroughfare between William Street and Queen Street will be open before Christmas, so that is good news as well. Scaffolding around the carpark will be removed in July.